Home›Blog›Cost Planning

Cost Planning

What is cost planning when you're the one pricing the job?

What is cost planning, and why do people keep using it as another word for estimating? The two are different jobs, and mixing them up is how a sound price turns into a loss you only spot at the final account.

Cost planning and estimating get used interchangeably, but they're not the same job. Estimating is putting a price on a defined scope of work. Cost planning is the ongoing process of controlling and tracking that price as the job moves from early drawings through construction to the final account. One's a snapshot. The other's a process.

If you're a builder or subcontractor wondering what is cost planning in practical terms, the honest answer is that you've probably done both without calling either by name. The difference matters most at the moment you stop looking at the numbers, which for a lot of contractors is the day the job is won.

What is cost planning, compared with estimating?

Think of the estimate as the answer to one question: what will this scope cost to build? You measure it, price it, add your preliminaries and margin, and send it.

A cost plan asks a different set of questions, and keeps asking them. What did we think each part of the job would cost? What do we know now that we didn't then? Where is the money going, and does the total still hold?

So the estimate feeds the cost plan. It doesn't replace it. A good estimate, measured properly and broken into elements, is the best starting point a cost plan can have. A lump sum with no breakdown is close to useless for it, because there's nothing to track against.

Three stages, three levels of detail

Early in a job, before drawings are developed, a cost plan is broad. Usually it's a figure per element based on similar work you've priced before. Nobody pretends it's precise.

As drawings develop, that becomes a more detailed plan, still elemental but with quantities behind each figure. The roof isn't just "roof" any more; it has an area, a build-up and a rate.

By the time the job's ready to go to site, the plan should be built from a full elemental breakdown measured against NRM2, priced item by item rather than as a round sum per element. At that point the cost plan and the bill of quantities are describing the same job in the same way, which is exactly what you want. There's more on that link in keeping the cost plan and the BoQ on the same numbers.

An estimate tells you what the job should cost. A cost plan tells you whether it still will.

What a cost plan actually contains

Strip away the jargon and a working cost plan has a fairly short list of parts. If any of these is missing, it's an estimate with a different title on the front.

  • An element structure. Substructure, frame, roof, external walls, finishes, services and so on, kept the same from first sketch to final account.
  • Quantities behind the figures. Once drawings allow it, each element is measured, not guessed.
  • Separate cost types. Labour, materials, plant, subcontract and preliminaries shown apart, so you can see which is moving.
  • Assumptions and exclusions. What was unknown at each stage, written down.
  • A record of changes. Every variation and design change logged against the element it affects, with its effect on the total.
  • A current forecast. Not just spend to date, but what each element is expected to cost by the time it's finished.

That last line is the one that turns a document into a control tool.

Why the distinction matters on site

Treating a cost plan as a one-off number instead of a live process is how jobs lose control. If nobody's comparing what's actually happening on site against the plan as the job progresses, you don't find out you're overspent until the final account, by which point there's no way to claw it back.

Say your groundworks element was priced on a straightforward strip foundation. On site, the trenches have to go deeper in one corner. If that extra depth gets recorded against the substructure element the week it happens, you can see the effect straight away, raise it with the client if it's their risk, and look for savings elsewhere if it's yours. If it only surfaces when someone reconciles invoices months later, all you can do is absorb it.

Same event, same cost. The only difference is when you found out.

Where it usually breaks down

The two most common failures are a scope that was never properly agreed, so the plan is chasing a moving target, and poor communication between whoever built the plan and whoever's actually running the job. Both are avoidable, and both come down to treating cost planning as paperwork rather than a tool you actually use week to week.

A quieter failure is the plan that's too coarse to be useful. If the whole of the internal fit-out is one line, you can't tell whether the overspend is in plastering, joinery or decoration. You just know the line is red. Enough detail to point at the problem is the minimum.

And then there's the plan nobody updates after a design change, because "we'll sort it at the end". That's the same as not having one.

A simple test: snapshot or process?

Here's how to tell which one you've got. Ask whoever holds the numbers what the job is forecast to cost at completion, today, element by element. If they can answer from the document, it's a cost plan. If they need to go away and work it out, it's an estimate that stopped being looked at.

So when someone asks what is cost planning, that's the short answer: the process that makes that question easy to answer at any point in the job.

If you'd rather start from a properly structured base, our cost planning services UK contractors use build the plan from your drawings, measured to NRM2 and priced on current rates local to the job. You can see how the breakdown is laid out in the sample estimate before committing to anything.

Common questions

Is cost planning only for large projects? +
No. The scale changes, but even a single extension benefits from knowing, element by element, whether the job is still tracking the price you gave.